Planning a Survey · November 7, 2026 · 4 min read

What to Send Your Surveyor Before the First Layout Visit

A checklist of drawings, CAD files, control, schedules and site details to send your construction surveyor before the first layout visit, and why each matters.

Total station display showing stakeout values beside a concrete foundation under construction

Key points

  • Send issued-for-construction drawings in both PDF and CAD, with the coordinate system and datum.
  • Existing control and benchmarks are the first thing a surveyor checks on site.
  • A few days of lead time lets calculations be checked in the office instead of in the truck.

Before the first layout visit, send your surveyor the issued-for-construction drawings in PDF and CAD, the coordinate system and datum, any existing control, the pile schedule and gridline plan if they apply, a site contact, the site's orientation requirements and your schedule. With those eight things in hand, the layout can be calculated and checked before the crew leaves the office.

Most first-day delays on a layout job come from something missing on that list. Here is what each item is for.

What does a surveyor need before layout?

  1. Issued-for-construction drawings in PDF.
  2. The same drawings in CAD.
  3. The coordinate system and vertical datum.
  4. Existing control points and benchmarks.
  5. The pile schedule and pile location plan, if there are piles.
  6. The gridline plan with dimensions.
  7. A site contact with a phone number.
  8. Orientation, safety and access requirements.
  9. The schedule and the sequence of work.

Why send both PDF and CAD drawings?

The PDF is the contract document. It carries the revision, the stamp and the written dimensions, and it is what governs if there is a disagreement. The CAD file is what makes the calculation fast and reduces the chance of a typing error, because points can be taken from the linework instead of being rebuilt from dimension strings.

Neither is enough alone. CAD linework is sometimes drawn out of scale or left behind when a dimension is revised, so we check the CAD against the written dimensions on the PDF and flag anything that does not agree. When only PDFs are available, the geometry is rebuilt from the dimensions, which takes longer. Send the architectural, structural and civil sets together. Conflicts between them are common, and it is better to find them at a desk than in the formwork.

Send the current revision and say so. Layout from a superseded drawing is one of the most expensive mistakes on a site, and the surveyor has no way to know a newer set exists unless someone says so.

What coordinate system and datum is the project on?

The civil drawings are usually drawn in real coordinates. In Alberta that is commonly 3TM or UTM, sometimes with a ground scale factor, or a local site or plant grid. Elevations refer to a vertical datum, and the drawings should say which one. Structural and architectural drawings are often drawn at an arbitrary origin and have to be placed on the site by the civil plan or by dimensions from known features.

If the system and datum are stated on the drawings, point us to the note. If they are not, tell us who did the original topographic survey. A mismatch in datum can put the whole building high or low, and a missed scale factor shows up as gridlines that do not fit across a long site.

GNSS base station and flagged stakes on a freshly cleared construction site
A GNSS base station set up on a cleared site with stakes in the ground.

Why does existing control matter so much?

Control points and benchmarks are what tie the drawings to the ground. If the site already has control from the design survey, a previous phase or another contractor, send the coordinate list, the elevations and a sketch or description of where the points are. The first thing the crew does on site is measure between those points to confirm they agree with each other and have not been disturbed.

If there is no control, say so. Establishing it becomes part of the first visit and needs time in the schedule. See control surveys and benchmarks for what that involves.

What about the pile schedule and gridline plan?

For pile layout, the pile location plan shows where each pile goes and the pile schedule gives its number, type, size and cut-off elevation. Stakes are numbered to match the schedule so the rig crew, the inspector and the as-built report all use the same names. Include the specified tolerances if you want the as-built report to flag piles against them.

The gridline plan is the skeleton of the building. Every footing, column and anchor bolt is dimensioned from it. A gridline plan with a full set of closing dimensions lets us check that the strings add up before anything is staked.

What site details should you pass along?

  • Site contact: the person who can say what is ready, what offsets the trades want and where stakes will survive.
  • Orientation and safety: site orientation, required tickets, PPE, vehicle requirements and any permits. On industrial sites these can take a day or more to complete, so they need to be booked ahead.
  • Access: gate hours, escorts, parking and whether the crew can drive to the work area.
  • Site condition: what is cleared, excavated or backfilled, and what equipment will be working nearby.
  • Offsets: the offset distance each trade prefers, so stakes are set once.
GNSS rover and base receivers set up beside safety fencing on a civil construction site
GNSS equipment set up beside safety fencing on a construction site.

How much lead time does a surveyor need?

For a simple job with good drawings, a day is often enough, and next-day crews are often available in the Edmonton region. A few days is better. It gives time to calculate the layout, have it checked by a second person in the office, and raise questions while the designer can still answer them. For remote and industrial sites, allow for orientations and travel.

Tell us the sequence as well as the start date. If the excavation is staked Monday, footings Thursday and anchor bolts the week after, the calculations can be prepared in that order and visits can be combined where the timing allows. That is one of the main ways to control cost, as explained in what construction surveying costs in Alberta.

Ready to send a package? Attach it to the quote form, or call (587) 714-2362 if you would like to go through the list first.

Book a crew

Need a crew on site?

Send the drawings and your schedule. You will have a written quote back the same day in most cases.

CallRequest a quote