Construction surveying service
Gridline, Anchor Bolt and Column Layout
Gridlines carried up through the structure, anchor bolt templates set and checked before the pour, and as-builts issued before steel arrives.
Gridlines and anchor bolts surveys in Alberta
Structural steel is fabricated to the drawings, not to the site. If anchor bolts are out, the columns do not fit and the erector is standing by while someone decides whether to core, weld or re-pour.
We set gridlines and anchor bolt groups from the same control used for the foundations, check templates for position, rotation and projection before concrete is placed, and survey the bolts again once the pour has cured. The steel fabricator and erector get an as-built report before the first truck leaves the shop.
Scope
What is included
- 01
Primary and secondary gridlines
Gridlines set on footings, walls and slabs with offset lines for formwork and layout by the trades.
- 02
Anchor bolt groups
Bolt group centres and orientation set out, with templates checked in place before the pour.
- 03
Projection and elevation
Top-of-bolt and top-of-concrete elevations checked against the base plate details.
- 04
Embeds and sleeves
Embed plates, sleeves and blockouts located in walls and slabs.
- 05
Columns and cores
Column centres, shear walls and elevator cores set out on each level and checked for plumb.
- 06
Pre-steel as-built
Every bolt group surveyed after the pour and compared to design so problems are found before erection.

Deliverables
What you get back
- Gridline marks and offsets on each level
- Anchor bolt as-built report with deviation in each axis and elevation
- Marked-up plan of any bolts outside tolerance
- CAD file of as-built bolt and gridline positions
Gridlines and anchor bolts: common questions
When should anchor bolts be surveyed?
Twice. Once when the template is fixed in the formwork, so it can still be adjusted, and once after the concrete has set, because templates move during the pour. The second survey is the one the steel erector relies on.
Can you transfer gridlines to upper floors?
Yes. Control is carried up the structure through openings or from outside the building and checked against the level below, so the grid does not drift as the building rises.
What if bolts are found out of tolerance?
The report shows exactly how far and in which direction, which is what the engineer needs to decide on a fix. Finding it before steel is on site keeps the repair small.
Related services
Often booked with this

Construction Layout and Staking
Building corners, gridlines, footings, walls, slabs and grades staked from your drawings and checked before they are handed to the trades.
Read more
Pile Layout and Pile As-Built Surveys
Driven, screw, helical and bored piles staked ahead of the rig, then surveyed after installation with deviation and cut-off reports.
Read more
As-Built Surveys
What was actually built, measured and compared against design: foundations, structures, utilities, roads and finished grades.
Read moreAvailable across Alberta: Edmonton, Sherwood Park, Calgary, Fort McMurray, Grande Prairie, Red Deer, Fort Saskatchewan and the Industrial Heartland, Leduc and Nisku, Cold Lake, Lloydminster, Peace River, Whitecourt, Hinton and Edson, Lethbridge, High Level.
Quotes
Quote for gridlines and anchor bolts
Tell us where the site is, what needs to be staked or measured and when. We reply the same day with a written quote, and a copy of your request is emailed to you straight away.
- 1Send the requestSite location, scope and schedule. Drawings can follow by email.
- 2Get a written quoteCrew rate or lump sum, with what is included stated plainly.
- 3Crew on siteLayout calculated and checked before the crew arrives.