Key points
- Pile surveying has two halves: layout ahead of the rig and an as-built of every installed pile.
- Oil sands sites run on a plant coordinate system, so the control has to be confirmed before the first pile is marked.
- The allowable pile deviation comes from your specification, and the as-built report shows each pile against it.
Pile surveying on an oil sands project means two jobs. The first is marking every pile location ahead of the rig, in the plant coordinate system, numbered to match the pile schedule. The second is measuring each installed pile afterward so the engineer can accept it and the cap, grade beam or module that sits on it will fit.
Alberta Construction Surveying provides pile layout and pile as-built surveys across northern Alberta, including Fort McMurray, Conklin, Wabasca, Cold Lake, Peace River, Grande Prairie and High Level. This article covers what the work includes, how it changes with the pile type, and what to send so the crew is ready when the rig is.
What does a pile survey include?
- A check of site control and benchmarks against the plant grid and datum before anything is marked.
- Pile centres set with a pin, lath or paint and numbered to match the pile schedule.
- Offset or reference points set outside the rig's working area, so a lost mark can be put back quickly.
- Cut-off elevations marked on installed piles from site benchmarks.
- An as-built survey of each pile: position at cut-off and top-of-pile elevation, compared to design.
- A deviation table and plan that flag any pile outside the tolerance in your specification.

Which pile types do we lay out?
The survey method is similar for every pile, but the timing and the checks change with how the pile goes in.
| Pile type | Where it is common | What the surveyor watches |
|---|---|---|
| Driven steel (pipe and H) | Pipe racks, equipment, buildings | Centre mark plus offsets that survive the rig. As-built after driving and again at cut-off if required. |
| Screw and helical | Pipe racks, skids, modular buildings, light structures | They install quickly, so layout has to stay well ahead. Position and top elevation are recorded for each pile. |
| Bored and cast-in-place concrete | Heavy equipment, tanks, larger structures | Centre set before drilling and checked again before the pour, along with any dowels or anchor bolts cast into the top. |
| Precast concrete | Buildings and industrial facilities | Laid out like driven steel. Head position and elevation are measured after driving. |
| Sheet piles | Excavation support, containment, cofferdams | The wall line is staked on an offset with corners and end points marked. Alignment and top elevation are as-built. |
| Micro piles | Tight access and work on existing foundations | Often inside or beside operating equipment, so control is carried in by total station. |
Why is pile layout on oil sands sites different?
Most oil sands and in situ facilities use a plant grid and a site datum instead of a standard map projection. The first task on any new area is to find the control the design was based on, measure between the points, and confirm they agree with each other and with the drawings. A pile field staked from the wrong benchmark is expensive, because the modules and pipe spools that land on it were fabricated to the design.
Pile fields are also large. A pipe rack or module yard can have hundreds of piles, and the rig moves faster than most people expect. We stake in blocks that follow the rig's sequence so marks are fresh when they are used and have not been driven over. Much of this work happens in winter, when frozen ground gives equipment access to soft areas. Paint does not hold on snow, so marks go on lath or pins, and control is rechecked through freeze and thaw.

What goes in a pile as-built report?
The report lists each pile by number with its design northing, easting and cut-off elevation, the measured values, and the difference in each direction. A plan shows the as-built positions against the design. Piles outside the specified tolerance are flagged so the engineer of record can decide what to do before the cap or grade beam is formed. Measurements are taken by total station from project control, which is good to a few millimetres over normal site distances. Reports are usually issued the next business day, in PDF with CSV and Civil 3D files.
Which regions do we cover?
We are based in Sherwood Park and travel to site. Regular areas for pile work are the Athabasca oil sands around Fort McMurray, Conklin and Wabasca, the Cold Lake and Peace River oil sands areas, and the gas processing country around Grande Prairie and High Level. Crews arrive with the safety documentation and site orientation the facility requires. For a wider view of plant work, see industrial and oil sands surveys.
What should you send before the rig arrives?
- Pile location plan and pile schedule, issued for construction, in PDF and CAD.
- Control point coordinates and benchmark elevations, with the coordinate system and datum stated.
- The specified tolerances for pile position and cut-off elevation.
- The rig sequence and start date.
- Site access, orientation and permit requirements.
To price pile layout or as-builts for your project, call (587) 714-2362 or send the drawings through the quote form.